Member News | UP CARGO, INC. successfully dismantled the thermoelectric plant

25 Jun 2022 10:18 AM | Anonymous

Good News...

A multinational energy company established in Panama, city of Colón installs its facilities in 2015, 6 years later made the decision to withdraw its bases, for which it was necessary to hire a responsible company that would be in charge of dismantling the thermoelectric plant so that later their parts were shipped back to Honduras.

This great opportunity was offered to UPCARGO. UPCARGO Team took action to give their best in this new objective. The projections for the participation of this great project began in mid-2021. And it was finally developed in May 2022.

UPCARGO was in charge of the mobilization of 40 units, including 19 motors of 50-TON, transformers, cells, CO2 rooms, among other parts of the thermoelectric plant.

Their work consisted of route inspection, study of route diagrams, heavy lifting of cargo studies, prior coordination, preventive logistics.

The steps for this operation to be carried out were as follows:
1. Customs clearance and procedures
2. Crane service to dismantling the thermoelectric
3. Logistics mobilization of the engines, transformers, cells, CO2 rooms to the depot
4. Warehousing in intermediate depots.
5. Mobilization parts of the plants to the port in special equipment.



The development of this operation was approximately ended in 25 days, with their staff in the field in which their team gave their effort day after day so that the operation could be carried out without incidents, always complying with the quality standard of our services and for the client.

Congratulations to them for their excellent job!

Please feel free to contact with UP CARGO, INC. for the inquires/shipments from/to Panama.